| Question Code1627 | Question Which of the following choices describes the “story points”? | Answers 
 They are a relative measure of the effort needed to complete a story.
                                
                                 
                                
                                                             
 They a measure of development time only, test time is considered separately.
                                
                                                             
 They are a relative measure of the value of a story.
                                
                                                             
 They are a measure of time to complete a story.
                                
                                                             | 
| Question Code1631 | Question According to the Agile Manifesto, your highest priority is to __________. | Answers 
 minimize change requests
                                
                                                             
 satisfy the customer
                                
                                 
                                
                                                             
 get the job done on time
                                
                                                             
 achieve the desired ROI
                                
                                                             | 